Reviewing should be effortless, and with the LatestCram C4070-604 engine you can revisit any or all questions whenever you like, turning spare minutes into IBM System z Technical V5 progress and shaky answers into confident ones.
IBM C4070-604 Exam Overview:
IBM C4070-604 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Topic 1: System Operations and Management | - Performance and workload management basics - System initialization and monitoring |
| Topic 2: Storage and Data Management | - DASD and storage architecture - Data access methods and dataset types |
| Topic 3: IBM System z Architecture Overview | - Mainframe hardware components and architecture concepts - System z virtualization principles (LPAR, PR/SM) |
| Topic 4: Security and System Integrity | - RACF security fundamentals - Authentication and access control concepts |
| Topic 5: z/OS Operating System Fundamentals | - Job management and workload processing (JCL basics) - z/OS system structure and address spaces |
IBM System z Technical V5 Questions, Answered Honestly
- Storage and Data Management ()
- IBM System z Architecture Overview ()
- Security and System Integrity ()
IBM System z Technical V5 Sample Questions:
Which of the following best describes zEnterprise architectural advantages?
- A. Includes all IBM servers and storage systems
- B. Shared nothing architecture
- C. A centralized shared everything z/Architecture
- D. A System of Systems consisting of multiple architectures
Correct Answer: D 🗳️
A customer has a Power with AIX server farm with network connectivity to a zEnterprise processor. Which of the following would represent a potential zBX opportunity for this customer?
- A. The customer wants to move Linux virtual machines from the zEnterprise to a zBX so that the Linux applications can be closer to a Smart
- B. The customer wants to accelerate certain DB2 on zEnterprise queries.
- C. The customer wants to accelerate their DB2 on Power with AIX.
- D. The customer wants a stand-alone zBX with Power blades to free up floor space.
Correct Answer: B 🗳️
A customer technical staff has been briefed on migration to a z114 or z196. They are discussing the new features with the System z Technical Specialist. Which of the following customer statements is incorrect and must be corrected by the Technical Specialist?
- A. There is Plan Ahead option available for the I/O drawers
- B. The correct mix of I/O cage and drawers is configured based on the number and type of I/O features ordered
- C. Addition and removal of z196 I/O cage is disruptive
- D. The I/O drawers can be added or removed non-disruptively
Correct Answer: A 🗳️
A customer is considering a z196 with a zBX. Which of the following is the best action a specialist could take to ensure customer satisfaction?
- A. Mentor the customer on installing PowerVM and VMware
- B. Conduct a "Fit for Purpose Study"
- C. Conduct a z/VM Implementation Workshop
- D. Review the hardware support process and the HMC documentation for the z196 CPC and the zBX
Correct Answer: B 🗳️
The zEnterprise Technical Specialist is talking with the customer support group. The customer technical staff has made several statements regarding their individual understanding of the cabling for zBX racks. Which of the following customer statements is incorrect?
- A. All cables required to connect a zBX to a node are delivered by default.
- B. All cables required to implement and connect a zBX to the customer environment (LAN, SAN) must be ordered separately
- C. All cables required to implement and connect a zBX to the customer environment (LAN,SAN) are delivered by default.
- D. In order to connect a zBX correctly to a customer network detailed planning is necessary the evaluate the requirements (SFPs, cables)
Correct Answer: B 🗳️
Viewing page 1 out of 12 pages.
Viewing questions 1-5 out of 57 questions.