NEW QUESTION # 25
What is one purpose of the Supply Protection (SUP) feature?
- A. Reserve quantities for a category of customers
- B. Propose framework agreements with suppliers to secure supply quantities
- C. Sell products in the sequence of incoming customer orders
- D. Protect yourself from unreliable suppliers
Answer: A
NEW QUESTION # 26
What needs to be activated as a prerequisite for using a product allocation check? Note: There are 2 correct answers to this question.
- A. The availability check against product allocation for basic Available-to-Promise
- B. The availability check against product allocation in the context of aATP
- C. The availability check against product allocation in Sales and Distribution
- D. The availability check against product allocation per client
Answer: B,D
NEW QUESTION # 27
You want to implement cycle counting for some materials in your warehouse. Which settings are required? Note: There are 2 correct answers to this question.
- A. Configure cycle counting indicators
- B. Maintain counting dates
- C. Assign a cycle counting indicator to the relevant materials
- D. Assign a cycle counting indicator to the relevant storage location
Answer: A,C
NEW QUESTION # 28
Which of the following business areas are part of the Line of Business Supply Chain, but are covered in separate courses? Note: There are 2 correct answers to this question.
- A. Inventory Management
- B. Warehouse Management
- C. Transportation Management
- D. Advanced Order Promising
Answer: B,C
NEW QUESTION # 29
Which of the following process steps update the stock in transit? Note: There are 2 correct answers to this question.
- A. Post a goods receipt for a stock transport order
- B. Create a delivery for a stock transport order
- C. Post a stock transfer in two steps
- D. Post a goods issue for a stock transport order
Answer: A,D
NEW QUESTION # 30
What are key activities of the Prepare phase of the SAP Activate methodology? Note: There are 3 correct answers to this question.
- A. Data migration
- B. Project setup
- C. Customer self-enablement
- D. User training
- E. Starter system provisioning
Answer: B,C,E
NEW QUESTION # 31
What are features of the Stock Transfer without Delivery (BMH) scope item? Note: There are 2 correct answers to this question.
- A. You can monitor stock in transit
- B. You can enter planned delivery costs
- C. You can transfer quality inspection stock
- D. You can maintain shipping data manually
Answer: A,B
NEW QUESTION # 32
Which of the following key features does the Stock - Single Material app provide? Note: There are 2 correct answers to this question.
- A. Display the stock of a material by plant, by storage location, and by bin location
- B. Compare the stock with the safety stock value defined for the material
- C. Indicate if the selected material is a slow-moving material
- D. Display the stock history for each plant or storage location for the last 11 periods
Answer: B,D
NEW QUESTION # 33
How can business users create new analytics content? Note: There are 3 correct answers to this question.
- A. Change existing data sources by adding filters
- B. Change underlying database tables of standard data sources
- C. Create additional key figures in existing data sources
- D. Combine current and historical data
- E. Create new data sources via joins of standard data sources
Answer: B,C,E
NEW QUESTION # 34
From which sources can the system determine the shipping conditions during sales order creation?
Note: There are 3 correct answers to this question.
- A. The ship-to party
- B. The schedule line category
- C. The sales document type
- D. The material
- E. The sold-to party
Answer: A,C,E
NEW QUESTION # 35
Which of the following scenarios can be performed either using or not using shipping activities? Note:
There are 3 correct answers to this question.
- A. Return to supplier
- B. Goods receipt for external procurement
- C. One-step stock transfer between plants
- D. Goods issue for sales order
- E. Provision of subcontracting components
Answer: A,B,D
NEW QUESTION # 36
What is the purpose of the Starter system in the SAP S/4HANA Cloud implementation project?
- A. To conduct a blueprint workshop to identify all customer requirements for a completely customized solution
- B. To configure the customer's personalized solution for demonstration and testing during the Realize phase
- C. To demonstrate SAP Best Practices processes in a preconfigured system and identify customer personalization requirements
- D. To demonstrate the customer's personalized solution, including process flows, the organizational structure, and authorizations
Answer: C
NEW QUESTION # 37
What types of situations does Situation Handling support? Note: There are 2 correct answers to this question.
- A. role-based
- B. object-based
- C. message-based
- D. event-based
Answer: B,C
NEW QUESTION # 38
What are the available methods through which you can fill staging tables in the SAP HANA database of the target system? Note: There are 3 correct answers to this question.
- A. SAP Smart Data Access
- B. Customer's ETL tools
- C. SAP SQL Anywhere
- D. SAP HANA Smart Data Integration (SDI)
- E. XML templates
Answer: B,D,E
NEW QUESTION # 39
Which document do you use to initiate a supplier return process?
- A. A return purchase order
- B. A stock transport order
- C. A return sales order
- D. A return delivery
Answer: A
NEW QUESTION # 40
Which of the following options are available for creating inbound deliveries? Note: There are 2 correct answers to this question.
- A. Manually with reference to a purchase order
- B. Manually with reference to a material document
- C. Automatically when saving a purchase order
- D. Automatically with a background job
Answer: A,D
NEW QUESTION # 41
Which types of datasets are required for predictive scenarios? Note: There are 2 correct answers to this question.
- A. Testing Dataset
- B. Apply Dataset
- C. Training Dataset
- D. Active Dataset
Answer: B,C
NEW QUESTION # 42
Why is de-coupling your extensions from SAP S/4HANA Cloud required? Note: There are 2 correct answers to this question.
- A. To allow customers to take advantage of predefined user exits
- B. To guarantee the stability of the system
- C. To ensure extensions do not conflict with SAP software updates
- D. To enhance existing functionality within the application itself
Answer: B,C
NEW QUESTION # 43
Which of the following are outcomes of the Fit-to-Standard workshop? Note: There are 3 correct answers to this question.
- A. Identification of source code changes
- B. Finalized scope and integration requirements
- C. Solution impact on business processes
- D. Expert configuration definition
- E. Extensibility solutions to close gaps
Answer: C,D,E