[Oct-2021] Verified SAP Exam Dumps with C_TS422_2020 Exam Study Guide
Best Quality SAP C_TS422_2020 Exam Questions LatestCram Realistic Practice Exams [2021]
C_TS422_2020 Exam Certification Details:
| Duration: | 180 mins |
| Languages: | English |
| Cut Score: | 56% |
| Exam: | 80 questions |
| Level: | Associate |
| Sample Questions: | SAP C_TS422_2020 Exam Sample Question |
SAP S/4HANA Production Planning and Manufacturing Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books | Weighting |
|---|---|---|
| Master Data in SAP S/4HANA | Identify and explain production relevant master data, including, but not limited to: bill of material, routing and production version. TS421, TS422 (SAP S/4HANA 2020) | > 12% |
| Production Orders in SAP S/4HANA | Determine BOM item category, describe order status management and set user statuses, configure availability check for components, trigger routing selection, set up an order type, apply material staging and confirmation. TS421, TS422 (SAP S/4HANA 2020) | > 12% |
| Introduction to SAP S/4HANA Supply Chain Planning | Outline both motivation and background of SAP S/4HANA, describe its main components, the lines of business, and the SAP User Experience strategy. TS421, TS422 (SAP S/4HANA 2020) | < 8% |
| Material Requirements Planning in SAP S/4HANA | Select and apply planning strategies, use the planning table, characterize long-term planning and master production scheduling, outline MRP basics and steps of MRP, and describe lot size procedures. TS421, TS422 (SAP S/4HANA 2020) | 8% - 12% |
| Advanced Planning in SAP S/4HANA | Outline the basics and master data of advanced planning, explain tools (alert monitor, detailed scheduling planning board) and advanced planning and detailed scheduling processes, explain planning evaluation concepts TS421, TS422 (SAP S/4HANA 2020) | > 12% |
| Process Orders in SAP S/4HANA | Characterize process order elements and process order processing, determine master data objects for process orders, identify features for Good Manufacturing Practices (GMP). TS421, TS422 (SAP S/4HANA 2020) | < 8% |
| Capacity Planning in SAP S/4HANA | Outline best practices for using SAP S/4HANA, describe the SAP HANA database concept and new user experience with SAP Fiori, outline the capabilities of embedded analytics. TS421, TS422 (SAP S/4HANA 2020) | 8% - 12% |
| Demand Management in SAP S/4HANA | Explain and compare the different production methods in make-to-order, make-to-stock, and assembly planning. TS421, TS422 (SAP S/4HANA 2020) | < 8% |
| Lean Manufacturing in SAP S/4HANA | Identify repetitive manufacturing specific master data, explain line load planning and confirmation, outline Kanban master data and Kanban processes. TS421, TS422 (SAP S/4HANA 2020) | 8% - 12% |
| Introduction to SAP S/4HANA Production Planning | Outline production planning components and functions, differentiate consumption-based planning vs. MRP, outline new trends in production planning. TS421, TS422 (SAP S/4HANA 2020) | < 8% |
NEW QUESTION 23
Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.
- A. Move time
- B. Wait time
- C. Float before production
- D. Pick/pack time
- E. Queue time
Answer: B,D,E
NEW QUESTION 24
In the Schedule Production app, which settings can you make in the planning strategy? Note: There are 3 correct answers to this question.
- A. Planning mode (bucket/sequence)
- B. Direction (forward/backward)
- C. Fixed pegging (on/off)
- D. Finiteness level (0...1)
- E. Scheduling control (finite/infinite)
Answer: A,B,E
NEW QUESTION 25
When can the material availability check occur automatically in a production order? Note: There are 2 correct answers to this question.
- A. At order confirmation
- B. At order settlement
- C. At order creation
- D. At order release
Answer: C,D
NEW QUESTION 26
If you use floats to limit dispatching in capacity planning, what type of time element can be reduced by strategy settings while dispatching?
- A. Production time
- B. Minimum wait time
- C. Goods receipt processing time
- D. Queue time
Answer: D
NEW QUESTION 27
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers tothis question.
- A. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
- B. Add the agreement to the quota arrangement and mark it for MRP relevance.
- C. Add the agreement to the source list and mark itfor MRP relevance.
- D. Set the creation indicator for purchase requisitions on the initial screen of the MRP run.
Answer: A,C
NEW QUESTION 28
Which time elements can be reduced by a reductionstrategy? Note: There are 3 correct answers to this question.
- A. Float after production
- B. Wait time
- C. Move time
- D. Goods receipt processing time
- E. Queue time
Answer: A,C,E
NEW QUESTION 29
An issue storage location was NOT found through the work center, bill of material (BOM)item, or material master. Whatdetermines whether the storage location can be derived from the production version?
- A. MRP Profile
- B. MRP Controller
- C. MRP Group
- D. Plant Data
Answer: C
NEW QUESTION 30
The MRP run detected a shortage of a material that you source from an external supplier in full pallets. How can you make sure you will only receive full pallets?
- A. Use the minimum order quantity.
- B. Use the MRP type for vendor managed inventory.
- C. Use the reorder point.
- D. Use the fixed lot size procedure.
Answer: D
NEW QUESTION 31
How can you carry out cost object controlling for production orders? Note: There are 2 correct answers to this question.
- A. Product-related
- B. Milestone-related
- C. Order-related
- D. Cost-related
Answer: A,C
NEW QUESTION 32
When working with both cross-plant and plant-specific material statuses in the mater al master, which status has the highest priority?
- A. The cross-plant status
- B. The least restrictive status
- C. The most restrictive status
- D. The plant-specific status
Answer: C
NEW QUESTION 33
If the stock level drops below the reorder stock in reorder point planning, what is the system logic to trigger procurement?
- A. Fill up to the reorder stock level
- B. Fill up to the safety stock level
- C. Fill up based on the lot size procedure
- D. Fill up to the maximum stock level
Answer: C
NEW QUESTION 34
Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?
- A. When multiple production versions are maintained for one product
- B. When multiple planned orders exists in one resource
- C. When multiple operations are maintained for one product
- D. When alternate resourcesare used within one operation
Answer: D
NEW QUESTION 35
You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?
- A. Forecast planning
- B. Consumption-based planning
- C. Material requirements planning
- D. Manual planning without check
Answer: B
NEW QUESTION 36
How would you define pegging in the context of Advanced Planning?
- A. An evaluation that is ordered according to thebill-of-material structure of all related products and represents the relationship between the receipt and the issue elements.
- B. An evaluation to verify if there are mater al or capacity shortages in the network after the production planning run.
- C. An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run.
- D. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements.
Answer: A
NEW QUESTION 37
You run MRP for a material that was planned using Demand-Driven Replenishment. Toward which buffer level does the MRP run create a replenishment proposal?
- A. Top of Red
- B. Top of Red Base
- C. Top of Green
- D. Top of Yellow
Answer: C
NEW QUESTION 38
Which SAP solutions support the supplier area in the portfolio of the Digital Value Network? Note: There are
3 correct answers to this question.
- A. SAP Concur
- B. SAP Ariba
- C. SAP Field glass
- D. SAP C/4HANA
- E. SAP SuccessFactors
Answer: A,B,C
NEW QUESTION 39
In which data objects do you maintain the production line as the work center forrepetitive manufacturing?
Note: There are 2 correct answers to this question.
- A. Repetitive manufacturing profile
- B. Routing
- C. Production version
- D. Production cost collector
Answer: B,C
NEW QUESTION 40
What does forecasting in the demand planning cycle include? Note: There are 3 correct answers to this question.
- A. Past quotation quantities
- B. Past procurement quantities
- C. One-off events
- D. Past sales order quantities
- E. Market intelligence
Answer: C,D,E
NEW QUESTION 41
In a production process, you need acertain amount of liquid as input material. The source tank is directly connected to the reactor. How can you process consumption postings?
- A. Kanban
- B. Picking list
- C. Transfer Order
- D. Backflushing
Answer: B
NEW QUESTION 42
Which SAP solutions can be used for forecast ng in Supply Chain Planning? Note: There are 2 correct answers to this question.
- A. Supply Chain Management (SCM)
- B. Integrated Business Planning (IBP)
- C. Material Requirements Planning (MRP)
- D. Capacity Requirements Planning (CRP)
Answer: A,B
NEW QUESTION 43
......