C_IBP_2305 Exam Dumps - PDF Questions and Testing Engine [Q11-Q32]

Share

C_IBP_2305 Exam Dumps - PDF Questions and Testing Engine

C_IBP_2305 Dumps - The Sure Way To Pass Exam

NEW QUESTION # 11
You need to make manual adjustments to your S&OP plan.Which are possible ways of making these changes?Note: There are 2 correct answers to this question.

  • A. Leveraging the web-based planning capability
  • B. Leveraging the functionality of SAP Workzone
  • C. Using Driver-Based planning
  • D. Using Microsoft Excel planning views

Answer: A,D


NEW QUESTION # 12
Which of the following data inputs, when increased, will always cause an increase in the safety stock outputs when the Global (multi-stage) Inventory Optimization operator is run?Note: There are 2 correct answers to this question.

  • A. Target Service Level
  • B. Holding Cost Percentage
  • C. Transportation Lead Time Error CV
  • D. Minimum Lot Size

Answer: A,D


NEW QUESTION # 13
What are some of the prerequisites for configuring a planning area that results in a successful consistency check?Note: There are 2 correct answers to this question.

  • A. Configure at most two input key figures on the same planning level in a key figure calculation.
  • B. Specify a planning horizon in the planning area for each level of the assigned time profile.
  • C. Configure at least one calculated key figure for the planning area.
  • D. Assign the compound master data type and its component master data types.

Answer: B,D


NEW QUESTION # 14
You have set up a planning area, and data is now available. You adjust the necessary time profile settings and run a consistency check.Which settings can you change and still run a successful consistency check?Note:
There are 2 correct answers to this question.

  • A. Add a new time profile level to the time profile.
  • B. Change the numbering hierarchy of the period IDs in the time profile.
  • C. Change the description of the attributes in the time profile.
  • D. Change the past and future horizon of the levels in the time profile.

Answer: C,D


NEW QUESTION # 15
Which sets of chart types are provided within the Analytics Advanced application?Note: There are 3 correct answers to this question.

  • A. Simulation Chart Types
  • B. Geographic Chart Types
  • C. Comparison Chart Types
  • D. Trend Chart Types
  • E. Seasonal Chart Types

Answer: C,D,E


NEW QUESTION # 16
You are modeling a new product introduction.Which of the following steps can be part of your modeling process in the Manage Product Lifecycle app?Note: There are 2 correct answers to this question.

  • A. Enter the product family to which the new product belongs
  • B. Copy the launch dimension from the reference product to the new product
  • C. Enter the Phase-out Start Date and Phase-out End Date
  • D. Create planning objects for new combinations in the app

Answer: B,D


NEW QUESTION # 17
You define fixing for a key figure.Which of the following functions are available for this key figure? Note: There are 2 correct answers to this question.

  • A. Fixing is possible for system editable key figures.
  • B. Fixing is possible for manually editable key figures.
  • C. Fixing is possible for a certain quantity of a key figure value.
  • D. Fixing is possible for a certain period, including all child values in the hierarchy.

Answer: A,D


NEW QUESTION # 18
Which of the following are valid use cases for using the Realignment App?Note: There are 2 correct answers to this question.

  • A. Merging two locations into a new location
  • B. Changing customer sources and reassigning customers to new DCs
  • C. Removing outliers from the sales history of a reference product before transferring its sales to a new product
  • D. Using the realignment run to identify obsolete data

Answer: A,B


NEW QUESTION # 19
What function would you use to configure a year-to-date calculation?

  • A. Cumulative Aggregation
  • B. Rolling Aggregation
  • C. Dynamic Rolling Aggregation
  • D. Last Period Aggregation

Answer: A


NEW QUESTION # 20
Safety Stock outputs from Multistage Inventory Optimization are sent to which of these processes? Note: There are 2 correct answers to this question.

  • A. Supply Heuristics in SAP IBP for sales and operations
  • B. Demand Sensing with Gradient Boosting (Full)
  • C. Charts creation in SAP Supply Chain Control Tower
  • D. Decoupling Points determination in SAP IBP for demand-driven replenishment

Answer: A,B


NEW QUESTION # 21
You are evaluating criteria for choosing the solver to support planning for a complex supply chain. What are some of the points that should be reviewed?Note: There are 2 correct answers to this question.

  • A. Planning results can be generated faster by the optimizer.
  • B. Push and Pull production models are used by the optimizer.
  • C. Finite heuristics can achieve demand prioritization and pegging.
  • D. Prioritization of demand elements one by one is achieved by unconstrained heuristics.

Answer: B,C


NEW QUESTION # 22
A time profile is defined with these levels: day, technical week, week, month, quarter, and year. What condition in configuration will allow you to have a different value in the current week, versus all other time buckets?

  • A. IF("PERIODID5" ="$$PERIODID5CU$$...)
  • B. IF("PERIODID4" ="$$PERIODID4CU$$...)
  • C. IF("PERIODID2" ="$$PERIODID2CU$$...)
  • D. IF("PERIODID3" ="$$PERIODID3CU$$...)

Answer: B


NEW QUESTION # 23
You are developing the functionality and appearance of the Excel UI for SAP IBP business users.Which extensibility capabilities for SAP IBP, add-in for Microsoft Excel are provided by Custom VBA coding?Note: There are 2 correct answers to this question.

  • A. SAP IBP ribbon extension
  • B. Changing the layout of the master data workbooks
  • C. Changing the member names
  • D. Changing the entries from the Name Manager

Answer: A,B


NEW QUESTION # 24
You are starting a new implementation project for SAP IBP and are considering the possible system architecture.What are the possible approaches for setting up the system landscape?Note: There are 2 correct answers to this question.

  • A. Create additional test planning areas in the production system to support cutover needs.
  • B. Set up a three-tier landscape using transport, starting from the development system to test and production.
  • C. Create additional planning areas in the test system to support training needs.
  • D. Set up a two-tier landscape, and have the configuration of the development system regularly updated from the production system.

Answer: B,D


NEW QUESTION # 25
Which constraints are taken into account by the Time-Series-Based Supply Planning Heuristic (Infinite)?Note: There are 3 correct answers to this question.

  • A. Adjusted transport receipts
  • B. Aggregated constraints
  • C. Maximum lot size
  • D. Minimum lot size
  • E. Transportation lead times

Answer: A,C,E


NEW QUESTION # 26
For which of the following application jobs can you enter planning filters as parameters?Note: There are 2 correct answers to this question.

  • A. Purge Key Figure Data
  • B. Purge Master Data
  • C. Create Time Periods for Time Profiles
  • D. Purge Non-Conforming Data

Answer: A,B


NEW QUESTION # 27
You have to be logged on to two separate SAP IBP tenants.What can help you differentiate the appearance of their user interfaces?Note: There are 2 correct answers to this question.

  • A. Having a different set of tiles in the Home group of apps.
  • B. Setting a separate theme for the Home page in the Web UI.
  • C. Add the system name and tenant information from the About section to the Home page.
  • D. Defining a different default planning area via the User Preferences.

Answer: B,C


NEW QUESTION # 28
Which conditions have to be fulfilled as a prerequisite to maintain a key figure disaggregation?Note: There are
2 correct answers to this question.

  • A. The key figure is calculated and all editable.
  • B. The key figure is stored and system editable.
  • C. The key figure is stored and all editable.
  • D. The key figure is calculated and system editable.

Answer: C


NEW QUESTION # 29
What does ABC/XYZ segmentation allow you to do?Note: There are 2 correct answers to this question.

  • A. Identify inventory items that require closer attention.
  • B. Choose time-independent key figures as segmentation measures.
  • C. Substitute missing values in case of sporadic demands.
  • D. Use forecasting algorithms that are specific to seasonal demands of SKUs in the segment "B".

Answer: A,B


NEW QUESTION # 30
You need to create time periods for the time profile in a planning area.What should you be aware of when running the Create Time Periods application job?

  • A. In the Parameter Section of the application job, choose the Time Profile ID and Planning Area.
  • B. This application job can be run for multiple time profiles at once.
  • C. The assigned Planning Area must be active.
  • D. A time profile has to be activated so that the application job can proceed.

Answer: A


NEW QUESTION # 31
Which of the following checks for master data and key figures does the Check Mode algorithm trigger?Note: There are 3 correct answers to this question.

  • A. It checks whether the required planning level master data exists for a subset of input key figures.
  • B. It checks whether the sourcing in the Production Source Item Master Data type exists.
  • C. It checks whether the location products specified in the master data are connected by customer sourcing rules within the supply chain network.
  • D. It checks whether the location resource specified in the master data forms a cycle in the supply chain network.
  • E. It checks whether the heuristic detects cycles formed by nodes (such as location products) in the supply chain network.

Answer: A,C,E


NEW QUESTION # 32
......

Pass SAP C_IBP_2305 Exam Quickly With LatestCram: https://www.latestcram.com/C_IBP_2305-exam-cram-questions.html

C_IBP_2305 Exam Questions (Updated 2024) 100% Real Question Answers: https://drive.google.com/open?id=1Rpj634V7QtAznKcdQ8QgN03Opmp5AG4S