Busy professionals, parents, students — the C_TSCM42_64 exam attracts all of them, and LatestCram serves all of them. 80 practice questions with verified answers, usable in the gaps of any schedule, on paper, offline on Windows, or in any browser.
SAP C_TSCM42_64 Exam Overview:
| Certification Vendor: | SAP |
|---|---|
| Exam Name: | SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 |
| Exam Number: | C_TSCM42_64 |
| Related Certifications: | SAP Certified Application Associate - SAP S/4HANA Production Planning SAP Certified Application Associate - Production Planning & Manufacturing (SAP ERP) |
| Real Exam Qty: | 80 |
| Exam Price: | Varies by region (~USD 500) |
| Certificate Validity Period: | No formal expiration (legacy certification validity may vary) |
| Exam Format: | Multiple Choice, Scenario-based Questions, Multiple Response |
| Passing Score: | 65% |
| Available Languages: | German, English |
| Exam Duration: | 180 minutes |
| Sample Questions: | ![]() |
| Exam Way: | Online proctored exam via SAP Certification Hub or authorized test centers |
| Pre Condition: | Basic knowledge of SAP ERP systems and manufacturing/production planning processes is recommended |
| Official Syllabus URL: | https://www.sap.com/training-certification.html |
SAP C_TSCM42_64 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Topic 1: Enterprise Structure in Production Planning | - Organizational Units in SAP ERP
|
| Topic 2: Production Orders and Execution | - Goods Movements
|
| Topic 3: Integration with Other SAP Modules | - CO and SD Integration
|
| Topic 4: Capacity Planning and Shop Floor Control | - Shop Floor Execution
|
| Topic 5: Master Data for Production Planning | - Bill of Materials (BOM)
|
| Topic 6: Material Requirements Planning (MRP) | - Procurement Proposals
|
| Topic 7: Demand Management and Planning | - Sales and Operations Planning (SOP)
|
C_TSCM42_64 Exam Questions & Answers
LatestCram refunds you in full if you take the SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 exam within 60 days of purchase and do not pass. The policy does not apply if the exam is taken within 3 days of purchase, if the exam was never actually taken, or to free materials or expired orders, and the candidate name must match the payer name. Submit a scan of your enrollment slip and the official Score Report PDF within 2 days of the exam; claims are processed within 7 days. Alternatively, exchange for two free exam products of equal value and keep your original update service. Delivery is by email within 1 minute of purchase — contact support if nothing arrives within 2 hours.
The C_TSCM42_64 exam is a SAP certification exam covering the SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 syllabus shown above. It forms part of these credential paths: SAP Certified Application Associate - Production Planning & Manufacturing (SAP ERP), SAP Certified Application Associate - SAP S/4HANA Production Planning. Most candidates are working people studying around jobs and families, which is why LatestCram built its 80 practice questions for fragmented schedules — PDF, Desktop Test Engine, and Online Test Engine formats included.
Online proctored exam via SAP Certification Hub or authorized test centers Register for the SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 exam through these official channels:
Once your date is confirmed, your LatestCram practice questions arrive by email within 1 minute, so the study clock starts immediately.
The official SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 outline divides the exam into 7 domains, the largest being Production Orders and Execution, Capacity Planning and Shop Floor Control, and Enterprise Structure in Production Planning. The full list is in the topics section above, and LatestCram's 80 practice questions address every domain in it.
Registration for the SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 exam costs Varies by region (~USD 500), and the passing score is 65%. Retaking means paying the fee again, so check your level with the LatestCram engines before you commit to a date.
Everything needed to start the minute your order arrives: 80 practice questions for the SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 exam in three formats — a printable, expert-prepared PDF with instant download; a Desktop Test Engine for Windows that simulates the real exam with two practice modes and works offline; and an Online Test Engine for any browser on Windows, Mac, Android, and iOS with test history and performance review. Also included: a free demo, 365 days of free updates, a 50% renewal discount afterward, unlimited installations, and remote installation guidance from professional IT staff if you need it.
SAP recommends these training resources for the SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 exam:
Reinforce the training with the 80 practice questions from LatestCram — short, frequent sessions fit working schedules better than marathon weekends.
Basic knowledge of SAP ERP systems and manufacturing/production planning processes is recommended Since requirements can change, confirm the current version on the official SAP exam page before scheduling.
The SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 exam contains 80 with a limit of 180 minutes. That is tight pacing — rehearse it in the LatestCram Desktop Test Engine's timed mode until it feels natural.
SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 Sample Questions:
A project team member analyzes the following situation in SAP ECC in the stock/requirements list for a finished product: there is only one customer order and one fixed planned order with a similar quantity amount. The customer order and the planned order both have deadlines on work days but not on the same work day; the planned order has a later deadline. The project team member cannot find a rescheduling message referring to this deadline misalignment in the stock/requirements list. What reasons could there be for the missing message? (Choose two.)
- A. The requirement coverage element is outside the rescheduling horizon.
- B. The elements are linked to each other via fixed pegging.
- C. The time misalignment falls within the tolerance window defined in Customizing.
- D. Requirement planning has not yet been carried out to update the rescheduling message.
Correct Answer: A,C 🗳️
A finished material is to be planned in a controlled manner in the SAP ECC system in the context of requirements planning. The planned orders are scheduled using what is known as basic date scheduling (not lead-time scheduling). Which of the following statements is true for the resulting dependent requirements?
- A. When a customer order is created for the finished product, the dependent requirements are automatically triggered for the components in the bill of material without a planning run.
- B. In multi-level backward scheduling, dependent requirements are triggered at the start date for the higher-level assembly planned order.
- C. If individual material components are explicitly assigned to operations during BOM and routing maintenance, the requirement dates of the dependent requirements for these components are scheduled at each of the operation start dates.
- D. In multi-level backward scheduling, dependent requirements are triggered at the start date for the higher-level assembly.
Correct Answer: D 🗳️
An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon is to be set equally for all materials by default. However, some materials are to be given a different planning horizon.
What procedure would you recommend to the project team for setting the planning horizon on the system side?
- A. The planning horizon is set in the plant parameters in Customizing and variant entries are stored in the material masters for the materials in question.
- B. The planning horizon is set in the MRP groups in Customizing and the variant values are stored in the material masters for the materials in question.
- C. The planning horizon is set in the MRP groups in Customizing and variant entries are assigned via the plant parameter settings.
- D. The planning horizon is set in Customizing using the plant parameter setting and variant entries are assigned via the MRP groups for the materials in question.
Correct Answer: D 🗳️
Which information is contained in production versions for selecting routings and bills of material?
- A. All the control parameters for selecting routings and bills of material
- B. The routing and BOM alternatives to be used for production
- C. The plant for which the routing and BOM have to be created
- D. The explosion date on which the validity of the routing and bill of material is checked
Correct Answer: B 🗳️
Which of the following statements about ATP (Available To Promise) checks for material components are correct? (Choose two.)
- A. ATP checks can be carried out automatically when releasing a production order.
- B. ATP checks can be adjusted to also consider future requirements and receipts.
- C. ATP checks are used to evaluate the free capacity on a certain work center.
- D. ATP checks are automatically performed during MRP (Material Requirements Planning) runs.
- E. ATP checks are mandatory for lead-time scheduling.
Correct Answer: A,B 🗳️
Viewing page 1 out of 16 pages.
Viewing questions 1-5 out of 80 questions.