Exams have been part of life since school, but our attitude toward them matures with age. Whatever your reason for pursuing PMI-RMP, LatestCram supports it with 336 practice questions for PMI Risk Management Professional, organized for serious preparation.
PMI PMI-RMP Exam Overview:
| Certification Vendor: | PMI |
|---|---|
| Exam Name: | PMI Risk Management Professional Certification Exam |
| Exam Number: | PMI-RMP |
| Exam Duration: | 150 minutes |
| Certificate Validity Period: | 3 years |
| Real Exam Qty: | 115 (100 scored, 15 unscored pretest) |
| Exam Format: | Scenario-based, Multiple-choice (single answer), Computer-based, Multiple-select (multiple answers) |
| Available Languages: | Arabic, Chinese (Simplified), English |
| Passing Score: | Not published; scaled scoring, approx. 75% accuracy recommended |
| Exam Price: | $520 USD (PMI members), $670 USD (non-members) |
| Related Certifications: | Project Management Professional (PMP) Program Management Professional (PgMP) PMI Agile Certified Practitioner (PMI-ACP) |
| Recommended Training: | PMI-RMP Official Exam Prep Course PMI-RMP Exam Content Outline |
| Exam Registration: | Pearson VUE Scheduling PMI Official Registration |
| Sample Questions: | ![]() |
| Exam Way: | Computer-based test at Pearson VUE centers or online proctored |
| Pre Condition: | Option 1: Secondary diploma + 36 months risk experience (last 5 years) + 40 hours risk education; Option 2: Bachelor's degree + 24 months risk experience (last 5 years) + 30 hours risk education; Option 3: Bachelor's from GAC-accredited program + 18 months risk experience (last 5 years) |
| Official Syllabus URL: | https://www.pmi.org/certifications/risk-management-rmp |
PMI PMI-RMP Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Risk Identification | 23% | - Identify internal and external risks - Document risks and characteristics - Apply identification techniques - Capture opportunities as well as threats - Update risk register |
| Risk Monitoring and Reporting | 19% | - Track effectiveness of responses - Update risk register and documents - Communicate risk status to stakeholders - Identify new and emerging risks - Capture lessons learned - Monitor identified risks and triggers |
| Risk Analysis | 23% | - Assess probability and impact - Prioritize risks - Perform quantitative risk analysis - Perform qualitative risk analysis - Use simulation and modeling techniques |
| Risk Response Planning | 13% | - Integrate responses into project plan - Select appropriate response actions - Assign owners and responsibilities - Develop response strategies for threats and opportunities |
| Risk Strategy and Planning | 22% | - Integrate risk management into project lifecycle - Create risk management plan - Develop risk management strategy - Align risk management with organizational and project objectives - Define risk appetite, threshold, and tolerance |
PMI-RMP Practice Questions FAQ
PMI-RMP is passed with Not published; scaled scoring, approx. 75% accuracy recommended, and the official exam fee is $520 USD (PMI members), $670 USD (non-members). Fixing these numbers early helps you set a measurable practice target.
PMI Official Registration: register for PMI-RMP
Pearson VUE Scheduling: register for PMI-RMP
The PMI-RMP exam contains 115 (100 scored, 15 unscored pretest) questions to complete in 150 minutes minutes. Rehearsing under the same limit on the LatestCram engine turns pacing into a trained habit.
PMI-RMP Official Exam Prep Course: Visit official page
PMI-RMP Exam Content Outline: Visit official page
Choose the version of PMI Risk Management Professional you want, one, two, or all three, add it to the cart, and complete payment through the secure Credit Card checkout. The download link then arrives by email within about a minute, so your study starts without wasted time.
The package includes 336 practice questions for the PMI-RMP exam. The count is set through analysis of a large volume of data, so the set matches the scope of the real test without padding.
- Risk Response Planning (13%)
- Risk Identification (23%)
- Risk Analysis (23%)
Divide your time according to each topic's weight.
Payment runs through the Credit Card system, a globally used online payment network. We never share your personal information with third parties without your permission, and we never send spam, so your details stay where they belong.
Option 1: Secondary diploma + 36 months risk experience (last 5 years) + 40 hours risk education; Option 2: Bachelor's degree + 24 months risk experience (last 5 years) + 30 hours risk education; Option 3: Bachelor's from GAC-accredited program + 18 months risk experience (last 5 years)
PMI Risk Management Professional Sample Questions:
A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?
- A. Perform a review of project documents
- B. Create prompt lists for expert interviews
- C. Analyze the assumptions and constraints
- D. Develop and employ an Ishikawa diagram
Correct Answer: D 🗳️
Explanation: Only visible for LatestCram members. You can sign-up / login (it's free).
A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.
Which data analysis tool should the risk manager use to forecast future performance?
- A. What-if scenario analysis
- B. Regression analysis
- C. Decision tree analysis
- D. Sensitivity analysis
Correct Answer: B 🗳️
Explanation: Only visible for LatestCram members. You can sign-up / login (it's free).
During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.
What could have been done during project planning to avoid overspending?
- A. Met weekly with the finance team to monitor the cost
- B. Engaged with the sponsor to buy the steel in advance of the project
- C. Properly documented the triggers and actions for the risk
- D. Communicated with the stakeholders that the project costs might increase
Correct Answer: C 🗳️
Explanation: Only visible for LatestCram members. You can sign-up / login (it's free).
In a complex project, individual risks have been identified with the stakeholders. The project sponsor asks the risk manager about the likelihood of project success. Which risk analysis tool(s) should the risk manager use as a basis for their response?
- A. Probabilistic and quantitative risk analyses to get the overall risk score
- B. Quantitative risk analysis to get the overall risk score
- C. Probabilistic risk analysis to get the overall risk score
- D. Qualitative risk analysis to get the overall risk score
Correct Answer: A 🗳️
Explanation: Only visible for LatestCram members. You can sign-up / login (it's free).
One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.
Which risk response strategy is the program manager using in this scenario?
- A. Transfer
- B. Enhance
- C. Escalate
- D. Exploit
Correct Answer: D 🗳️