Passing a difficult exam takes more than headstrong courage — it takes the right material, and choosing among thousands of study products is itself a challenge. LatestCram answers that choice simply: 266 practice questions for the PRINCE2-Practitioner exam, verified answers, and service that never clocks out.
PRINCE2 PRINCE2-Practitioner Exam Overview:
| Certification Vendor: | PeopleCert (AXELOS) |
|---|---|
| Exam Name: | PRINCE2 Practitioner Examination (6th Edition / PRINCE2 Practitioner) |
| Exam Number: | PRINCE2 Practitioner |
| Real Exam Qty: | 68 questions |
| Exam Format: | Multiple-choice, Scenario-based questions, Objective testing, Open book (official PRINCE2 manual allowed) |
| Related Certifications: | PRINCE2 Agile Practitioner PRINCE2 Foundation |
| Available Languages: | Dutch, Spanish, French, Italian, German, English |
| Certificate Validity Period: | 3 years |
| Exam Duration: | 150 minutes |
| Exam Price: | Varies by region (typically ~£300–£500 GBP equivalent) |
| Passing Score: | 55% (approx. 38 out of 68) |
| Recommended Training: | PRINCE2 Accredited Training Organizations (ATO list) PRINCE2 Official Training (PeopleCert) |
| Exam Registration: | PeopleCert Official Registration |
| Sample Questions: | ![]() |
| Exam Way: | Online proctored exam or authorized test center (onsite) |
| Pre Condition: | PRINCE2 Foundation certification or equivalent project management knowledge is required before taking Practitioner exam. |
| Official Syllabus URL: | https://www.peoplecert.org/browse-certifications/project-management/prince2 |
PRINCE2 PRINCE2-Practitioner Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| PRINCE2 Processes | - Controlling a Stage - Directing a Project - Managing Product Delivery - Initiating a Project - Starting up a Project - Closing a Project - Managing a Stage Boundary |
| PRINCE2 Principles | - Focus on products - Manage by exception - Manage by stages - Continued business justification - Learn from experience - Defined roles and responsibilities - Tailor to suit the project |
| PRINCE2 Themes | - Plans - Quality - Business Case - Organization - Risk - Change - Progress |
PRINCE2 Practitioner Prep: Three Versions, One Verified Bank
- PRINCE2 Processes ()
- PRINCE2 Themes ()
- PRINCE2 Principles ()
PRINCE2 Practitioner Sample Questions:
Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2. Work is to start at the beginning of week 2 (Stage 4).
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements
8. Highlight Report every Monday by 10.00 am.
9. The report must contain a summary of all products worked on during the previous week.
10. Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion Which 2 statements apply to either the Reporting arrangements or Problem handling and escalation sections?
- A. Replace entry 8 with 'Checkpoint Report every Monday by 10.00 am' because Highlight Reports are intended for the Project Board.
- B. Delete entry 11 because the impact analysis should be provided when the issue is notified.
- C. Add 'Any risks identified to be added to the Risk Register' to Reporting arrangements.
- D. Move entry 10 to Problem handling and escalation because that section describes how issues are handled.
- E. Delete entry 9 because this level of detail is unnecessary.
Correct Answer: B,C 🗳️
Which of the following statements is False regarding the Risk Management Strategy?
- A. It documents the approach to risk
- B. It captures and maintains all relevant information on identified threats and opportunities
- C. It documents the risk tolerances
- D. It identifies responsibilities towards risk for the project
Correct Answer: B 🗳️
Product based planning focuses on which of the following:
1. Creating product descriptions
2. Identifying activities
3. Creating a Product hierarchy
4. Creating a Product sequence
- A. 1, 2, 3
- B. 1, 2, 4
- C. 1, 3, 4
- D. 2, 3, 4
Correct Answer: A 🗳️
Which of the following statements are True:
1. Quality management is the complete set of quality standards, procedures and responsibilities for a site or organization.
2. Quality planning is about defining products required of the project with their respective quality criteria, methods and responsibilities.
3. Quality control focuses on the operational techniques and activities used to carry out quality inspections
4. Quality assurance ensures that quality methods are being correctly followed.
- A. 1, 2 & 4
- B. 2, 3 & 4
- C. 1, 3 & 4
- D. 1, 2 & 3
Correct Answer: D 🗳️
It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.
Which product should show that the photos could be used for other promotional material for the company?
- A. Exception Report
- B. Benefits Review Plan
- C. Lessons Log
- D. End Project Report
Correct Answer: D 🗳️