Convenience for reading and printing
It is quite understandable that different people have different tastes (70-178 exam cram), and our company has taken which into consideration so that we have prepared three kinds of 70-178 latest practice material versions in our website for our customers to choose. Among which the PDF version is the most popular one, because it is universally acknowledged that the PDF version is convenient for you to read as well as printing. That is to say that after downloading our 70-178 cram file in PDF version you will have access to prepare for the exam wherever and whenever you want without any restriction. Please just have a try!
Fast delivery
If time be of all things the most precious (70-178 exam cram), wasting of time must be the greatest prodigality, our company has placed high premium on the speed of delivery. Since our 70-178 latest practice material are electronic files, we can complete the transaction only on the internet. As soon as you pay for the 70-178 cram file in the website, our operation system will record your information immediately then encrypt all of them in order to protect your personal information from leaking out, after that our operation system will send the 70-178 exam cram to the email which you used to register our website, the overall process will only take 5 to 10 minutes, in other words, you can start to prepare for the exam with 70-178 latest practice material only in a few minutes after payment.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
In the 21st century,we live in a world full of competition. In this industry, the examination is one of the most important tools (70-178 cram file) whether we have met the standard to be more professional in this field or not. As a worker, if you want to get the certification (70-178 exam cram), there is no doubt that you have to get prepared for exams in order to pass it. Some people may complain that there are too many exams in our lives, and the 70-178 exam is so complicated for the majority of the Microsoft workers, if you are one of those workers who are distracted by the exam, then today is your lucky day, since I will present a remedy for you in this website -- our latest 70-178 exam practice material. The advantages of our 70-178 cram file are as follows.
The most preferential prices
During the 10 years, our company has invested a lot of money in compiling the most useful and effective 70-178 exam cram for all of the workers, even though we still adhere to the original faith that we will provide help to as many workers as possible, hence, we have been always sticking to provide the most preferential prices for all of the workers (70-178 latest practice material). Now we have a large number of regular customers in many different countries, and there is no one but praises our 70-178 cram file. What's more, we will carry out sales promotion activities on unfixed date, you can keep an eye on our website especially in major festivals.
Microsoft 70-178 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Tracking and Controlling Projects | 25% | - Update progress and schedule
|
| Topic 2: Creating a Project Plan | 20% | - Create task relationships
|
| Topic 3: Viewing and Reporting Project Data | 20% | - Customize views and tables
|
| Topic 4: Configuring and Automating Projects | 10% | - Work with multiple projects
|
| Topic 5: Managing Resources and Assignments | 25% | - Create and configure resources
|
Microsoft Project 2010, Managing Projects Sample Questions:
Question 1
You manage several projects saved on a shared drive. You want to create a critical path relationship between several schedules managed by other project managers. You need to link the project schedules at the task level. You also need to ensure that each project manager can continue to manage their own project. What should you do?
A. -Open a blank project.
-Insert each project and select the Link to project option.
-Link tasks as needed.
-Save the subprojects.
B. -Open each individual project.
-Create date constraints for task deadlines.
-Save the project.
C. -Open a blank project.
-Insert each project and clear the Link to project option.
-Save the blank project as a new named project.
-Discard the subprojects.
D. -Open a blank project.
-Copy and paste each project into the new file.
-Link tasks as needed.
-Save the project by using a new name.
E. -Open a blank project.
-Insert each project and select the Link to project option.
-Save the blank project as a new named project.
-Discard the subprojects.
Question 2
You need to view the following information for your project: ?Current cost ?Baseline cost ?Actual cost ?Remaining cost ?Percentage of completion Which component will display the information?
A. The default Task Sheet
B. The default Resource Sheet
C. The Project Statistics window
D. The default Cost Table
Question 3
You create a custom Timeline view of summary tasks and key milestones. You need to send an image of only the custom Timeline view by e-mail. Which two actions could you perform? (Each correct answer presents a complete solution. Choose two.)
A. On the File menu, select Save & Send, and then click Create a PDF/XPS Document.
B. On the Format tab, select Copy Timeline, and then click For email.
C. Copy and paste the Timeline view into the body of the e-mail.
D. On the File menu, select Save & Send, and then click Send as Attachment.
Question 4
Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?
A. Update the base project calendar.
B. Assign the resource only to tasks that are scheduled on the working days.
C. Change the working time for the resource.
D. Change the maximum units for the resource.
Question 5
You need to ensure that when you add new tasks, the project schedule doesn't set a start date and end date. What should you do?
A. On the Schedule tab of the Project options, change the New tasks created option to Manually Scheduled.
B. Click New Tasks and change the option to Auto Scheduled.
C. Select Task from the main ribbon menu. Highlight the task that you want to change and select Manually Schedule.
D. On the Advanced tab of the Project options, clear the Automatically add new resources and tasks check box.
E. On the Display tab of the Project options, clear the Edits to start and finish dates check box.
Solutions:
| Question 1 Answer: A | Question 2 Answer: C | Question 3 Answer: A,D | Question 4 Answer: C | Question 5 Answer: A |